DIGEST OF CHANGES IN LEGISLATION IN THE FIELD OF ELECTRIC POWER INDUSTRY FOR JULY 2020
Adopted by the NPA The projects NPA

Adopted normative legal acts
LICENSING LAW
Date of entry
01.08.2020
For whom:
Owners of micro-generation facilities
What gives the consumer:
Contact a guaranteed supplier for the sale of electricity at a micro-generation facility
The essence of the changes
Consumers who own a micro-generation facility receive the right to sell the generated energy at the specified facility. The sale of electricity in this case is not an entrepreneurial activity
Consumers who own a micro-generation facility receive the right to sell the generated energy at the specified facility. The sale of electricity in this case is not an entrepreneurial activity.
Consumers who own a micro-generation facility receive the right to sell the generated energy at the specified facility. The sale of electricity in this case is not an entrepreneurial activity.
What do you need
Contact a guaranteed supplier for the sale of electricity at a micro-generation facility
Projects of normative-legal acts
The government will determine how to calculate the fee for connecting microgeneration facilities to the grid.
For whom:
Notice of the development
Status
Notice of the development
The placement of the text
Public comment
Regulatory impact assessment
Approval to the Federal authorities
Adoption of the NPA
The essence of the changes
The term of technological connection of power receiving devices up to 150 kW can be reduced from 6 months to 30 working days.
For whom:
Owners of microgeneration objects
Status
Notice of the development
The placement of the text
Public comment
Regulatory impact assessment
Approval to the Federal authorities
Adoption of the NPA
The essence of the changes
The government will postpone the selection of projects for the modernization of generating facilities of thermal power plants and cancel checks on compliance with the level of localization of production of equipment for the modernization of thermal power plants.
For whom:
Owners of microgeneration objects
Status
Notice of the development
The placement of the text
Public comment
Regulatory impact assessment
Approval to the Federal authorities
Adoption of the NPA
The essence of the changes
Data center operators can get preferential access to the electricity market.
For whom:
Owners of microgeneration objects
Status
Notice of the development
The placement of the text
Public comment (from 6 to 26 August)
Regulatory impact assessment
Approval to the Federal authorities
Adoption of the NPA
The essence of the changes
Rostekhnadzor regulates the procedure for issuing permits for the operation of energy-receiving and heat-consuming installations of consumers.
For whom:
Owners of microgeneration objects
Status
Notice of the development
The placement of the text
Public comment
Regulatory impact assessment
Approval to the Federal authorities
Adoption of the NPA
The essence of the changes

Changes in legislation in the electric power industry over the past periods
Date of publication: 20.02.2020
Learn




Our services